The client

A worldwide telecoms provider, acting on behalf of their client.

The challenge

We were asked to migrate more than 280 devices from an IBM environment to Wipro, including their checkpoint management, firewall and authentication services.

If our client failed to deliver this migration within the agreed timescales, they’d be liable for millions of pounds worth of penalties for leaving their client vulnerable to unnecessary network and security failures.

The solution

We sourced and dispatched a team of four to plan and deliver the solution at our customer’s premises.

We worked long days, many nights and weekends to successfully deliver the solution managing at least four other technical teams outside of our own in order to deliver a successful solution.

The results

• We successfully migrated all devices in the agreed timescale

• We saved our client from facing multi-million pound penalties